How to measure landscape production rates
To measure landscape production rates, measure each task’s quantity on the property, measure the time spent on that task over several visits, and divide quantity by time.
The hard part is the time, not the quantity. Most companies already know the turf area and edge length of a property; few know how many minutes of each visit went to mowing versus edging.
Step 1: Measure the quantities
Measure each task’s quantity once per property: turf area for mowing, hard edge length for edging, trim length, hard surface area for blowing, shrub counts. Aerial measuring tools are fast, but they miss areas under trees, shadows and overhangs, so confirm on a site walk.
Step 2: Measure the time per task
| Method | Per task? | Visits covered | Main drawback |
|---|---|---|---|
| Timesheets / job costing | No, per visit | All | Cannot split a visit into tasks |
| Stopwatch time study | Yes | The few someone watches | Costly, and crews work differently when watched |
| GPS time study | Yes, by zone | All | Needs zones drawn and phones carried |
Timesheets are where most companies start, and they give one blended rate per property. That is enough to spot a property that runs long, not enough to price mowing on the next bid. A GPS time study gives per-task time on every visit.
Step 3: Divide, then group
Divide each task’s quantity by its time to get a production rate, per person-hour so it survives changes in crew size. Then group properties that are alike: open turf vs. obstacle-heavy, flat vs. sloped. A rate from similar properties predicts better than one company-wide average.
Step 4: Flag the unusual days
Wet ground, irrigation repairs, a missed week of growth: leave those out of the normal rate, or keep them as their own adjustment. Otherwise one bad day skews every bid that uses the rate.
Step 5: Use the rate in the bid
Hours = quantity ÷ rate, adjusted for the property’s conditions. Hours × cost per hour is the labor line. Re-check the rate against actuals after the job starts; job costing shows whether the estimate held.
Motion Map does steps 2 to 4 from crew members’ phones and puts the resulting rates and margin on every bid.
Questions
How many visits do I need to measure a production rate?
A production rate from one visit is an anecdote. Several visits to the same property, ideally across different weeks, show the normal range and expose unusual days.
Can I measure production rates from timesheets?
Timesheets give one blended rate per property visit, which is useful for spotting properties that run long. They cannot give per-task rates such as mowing or edging, because a visit’s time is not split by task.